Close Menu

    Subscribe to Updates

    Get the latest creative news from FooBar about art, design and business.

    What's Hot

    Infinix launches NOTE 60 Series in Malaysia

    Razer’s laptop sleeve comes with MagSafe wireless charging for US$130

    Apple’s Rumoured Budget MacBook Could Arrive With Notable Feature Trade-Offs

    Facebook X (Twitter) Instagram
    • Artificial Intelligence
    • Business Technology
    • Cryptocurrency
    • Gadgets
    • Gaming
    • Health
    • Software and Apps
    • Technology
    Facebook X (Twitter) Instagram Pinterest Vimeo
    Tech AI Verse
    • Home
    • Artificial Intelligence

      What the polls say about how Americans are using AI

      February 27, 2026

      Tensions between the Pentagon and AI giant Anthropic reach a boiling point

      February 21, 2026

      Read the extended transcript: President Donald Trump interviewed by ‘NBC Nightly News’ anchor Tom Llamas

      February 6, 2026

      Stocks and bitcoin sink as investors dump software company shares

      February 4, 2026

      AI, crypto and Trump super PACs stash millions to spend on the midterms

      February 2, 2026
    • Business

      FCC approves the merger of cable giants Cox and Charter

      February 28, 2026

      Finding value with AI and Industry 5.0 transformation

      February 28, 2026

      How Smarsh built an AI front door for regulated industries — and drove 59% self-service adoption

      February 24, 2026

      Where MENA CIOs draw the line on AI sovereignty

      February 24, 2026

      Ex-President’s shift away from Xbox consoles to cloud gaming reportedly caused friction

      February 24, 2026
    • Crypto

      Palladium Price Approaches a Critical Turning Point

      February 28, 2026

      Trump to Takeover Cuba, Iran War Tensions Rise, Bitcoin Crashes Again

      February 28, 2026

      A 40% XRP Crash Couldn’t Shake Its Strongest Holders — Is $1.70 Still Possible?

      February 28, 2026

      Why Is the US Stock Market Down Today?

      February 28, 2026

      SoFi Becomes First US Chartered Bank to Support Solana Deposits

      February 28, 2026
    • Technology

      The compact smartphone I actually want: Xiaomi 17 in a Galaxy S26 world

      February 28, 2026

      Exciting laptop concept turns palm rest into an E ink notepad

      February 28, 2026

      AYN Thor and Odin 3 new pricing revealed, to take effect in March

      February 28, 2026

      External desktop graphics card on a mini PC, laptop or tablet? The Minisforum DEG2 makes it possible

      February 28, 2026

      Linux-based Orange Pi Neo gaming handheld delayed due to rising RAM and storage costs

      February 28, 2026
    • Others
      • Gadgets
      • Gaming
      • Health
      • Software and Apps
    Check BMI
    Tech AI Verse
    You are at:Home»Technology»The datacentre energy deficit: How worried should operators be about power outages?
    Technology

    The datacentre energy deficit: How worried should operators be about power outages?

    TechAiVerseBy TechAiVerseMarch 20, 2025No Comments8 Mins Read1 Views
    Facebook Twitter Pinterest Telegram LinkedIn Tumblr Email Reddit
    The datacentre energy deficit: How worried should operators be about power outages?
    Share
    Facebook Twitter LinkedIn Pinterest WhatsApp Email

    The datacentre energy deficit: How worried should operators be about power outages?

    There has now been close to £40bn in new datacentre investment announced in the UK since the new government came to power in July 2024, and started turning its rhetoric about wanting to support the growth of the server farm sector into reality.

    The government’s pro-growth stance towards the datacentre sector has landed well with industry stakeholders. Still, it cannot be ignored that long before Keir Starmer took over Number 10, concerns have circulated about the UK power grid creaking under the weight of demand from server farms.

    It’s a topic Computer Weekly has covered on multiple occasions over the past decade, and an issue that’s been gradually becoming more acute and urgent as the demand for UK-based compute capacity from the hyperscale community has grown.

    However, that was before we had a government in play that was intent on fast-tracking new datacentre developments to grow the economy by cashing in on enterprise and consumer demand for cloud-based services and artificial intelligence (AI). And with £40bn of new datacentre investment secured within the government’s first six months in power, it’s perhaps unsurprising that concerns about the impact all this potential development will have on the UK’s energy security and supply continue.

    Particularly considering the pressure the government is under to decarbonise the grid by phasing out and replacing fossil fuels with renewable sources.

    During a session at the March 2025 Datacentre World conference in London, Michael Drury, managing director of green energy consultancy Lucid Catalyst, said it’s a situation putting economies all around the world under pressure, as they figure out how to address the “energy gap” that could potentially open up in front of them.

    “If you ignore datacentres, you still have to think of the energy gap that we’ve got that’s coming along, especially in countries that have existing [fossil fuel] power generation that is dropping off, and [a need to] provide the amount of energy and the demand that’s needed there,” he said.

    Power consumption

    Figures from the International Energy Agency (IEA) show that 460 terawatt hours of power were consumed by datacentres globally in 2022, with the organisation predicting this figure could double to more than 1,000 TWh by next year.

    “If we look at how long it took to go from [zero] to 460 terawatt hours, the energy production timeline [shows] it took about 30 years,” said Drury.  

    “Additionally to that, we have the demand that’s growing outside of datacentres … so we have competition for that energy.”

    And the industry is all too aware of that. A survey of 400 IT and business leaders from across the UK and US by electronics and computational design firm Cadence, released in early March 2025, revealed that 70% of respondents had concerns that national power grids were being “stretched to their limits” by datacentre developments.

    Meanwhile, 83% said they had reason to believe their own datacentre developments are competing with residential energy demand, with 34% of this group “believing” the impacts of this to be great.

    “This is significant because strained grids increase the likelihood of outages for both datacentres and homes,” said Cadence, in its accompanying Datacentre evolution: The innovation imperative report.

    “This will not only have substantial financial implications for facilities, but will also increase public resistance to new datacentres and intensify pressure to make their operations more efficient.”

    Grid connectivity issues

    Ensuring there is enough power to go around is one thing, but another related issue is the time it takes for new developments to get connected to the grid.

    As detailed in the National Infrastructure Commission’s (NIC’s) February 2025 Electricity distribution networks: Creating capacity for the future report, businesses of all kinds – not just datacentres – will want firm assurances that they will be able to access the power they need on a consistent and reliable basis before they invest in developments.

    “And if a business can’t connect to the network promptly, they will delay investment decisions or worse, make those investments elsewhere, undermining the government’s growth mission,” the NIC report continued.

    Figures from energy market regulator Ofgem confirm there is a 400GW pipeline of grid connection requests, which estimates suggest would take 10-15 years to clear and fulfil.

    This delivery timeframe is undoubtedly problematic for datacentre developers looking to rapidly build out the infrastructure needed to help the UK government achieve its AI ambitions.

    Particularly as the process of assigning grid connections has traditionally operated on a first-come, first-served basis, and – as confirmed by Ofgem – many of these applications are speculative in nature and may never come to fruition, so are simply blocking the queue for others.

    What datacentre operators are left working with is a system where there are question marks over the surety of supply from the gird, and how long it will take to ensure they have a connection to it.

    Reasons for optimism

    And challenging though it may be, the picture is not as bleak as it could first appear. Ofgem, for example, set out plans in November 2023 to rid the grid connection queue of “zombie” projects from speculative developers.

    This reworked system means developers must meet certain non-negotiable milestones within their connection agreements, and failing to do so will result in their projects being forced out of the queue.

    The system also allows for energy generation and storage projects that will contribute to boosting the UK’s supply of energy to be fast-tracked.

    In further support of that, Ofgem announced plans in November 2024 to speed up the time it takes to connect new green energy generation projects to the grid by prioritising initiatives that can be operational within five years and meet certain location and voltage criteria requirements, in support of the government’s net-zero goals.

    Backup power supplies

    John Booth, chair of the Data Centre Alliance’s (DCA) Energy Efficiency Steering Group, also told Datacentre World attendees about the infrastructure investment the government is making to safeguard the supply of energy the UK also imports from other countries.

    “In the UK, we import anywhere between five to 15% of our energy from the interconnectors, [which] go across to France, Belgium, Netherlands, Norway and Ireland,” he said.

    Currently, the UK receives 9.8GW of power from these interconnectors, and the government has plans to increase this capacity to 18GW by 2030, said Booth.

    However, he also acknowledged that relying on interconnectors is a costly and potentially unsustainable way to ensure the UK has the power it needs to keep the lights on long-term. “This helps us in the short term, whilst we’re building our own capacity out, but for every pound that we spend on energy from the interconnectors is a pound that cannot be used in the UK to increase our capacity,” said Booth.

    Also on the panel was Louisa Cilenti, co-founder and chief legal officer of datacentre compliance company Clear Decisions, who said – despite how rapidly the demand profile and UK energy mix is changing – she believes the UK is positioned to “comfortably” meet its future energy demand.

    “The situation really does need quite careful planning and a lot more investment, [but] I think we’re going to be comfortably able to meet our future energy demand,” she said. “And I think the reason for that optimism is that we just have to look at our abundant renewable energy sources.

    “We are accelerating wind, solar and battery [power] at a phenomenal speed … so [the question is] how much quicker can we get them onto the grid … and can we get the right type of power to the right place at the right time that’s affordable for the customer?” said Cilenti.

    Picking up the conversation, Michael Clark, CEO of renewable energy consultancy Relode, said the UK has access to the energy it needs, but it is the underlying infrastructure and process involved with getting it to the right place at the right time that is the issue.

    “I see [the problem here as] less of an energy gap and more of an infrastructure gap, [because] the biggest problem we have is that we are in this demand space, where we are now competing with an exceptional volume of renewable energy [for grid connections],” he said.

    Clark name-checked the work Ofgem was doing to streamline the waiting list for grid connections for datacentres and renewable projects, but said more needs to be done.

    “We have to really challenge that team that’s taking six months to decide how to change things, [and ensure] they consider this new type of demand in parallel with the renewable connections that are already in the queue – and not sequentially behind them. That, for me, is the gap,” he said. “Infrastructure needs to be fixed before we look at the energy.”

    Share. Facebook Twitter Pinterest LinkedIn Reddit WhatsApp Telegram Email
    Previous ArticleNAS storage: TrueNAS aims to make it big in Europe
    Next Article Government considering redress scheme for families of Post Office scandal victims
    TechAiVerse
    • Website

    Jonathan is a tech enthusiast and the mind behind Tech AI Verse. With a passion for artificial intelligence, consumer tech, and emerging innovations, he deliver clear, insightful content to keep readers informed. From cutting-edge gadgets to AI advancements and cryptocurrency trends, Jonathan breaks down complex topics to make technology accessible to all.

    Related Posts

    The compact smartphone I actually want: Xiaomi 17 in a Galaxy S26 world

    February 28, 2026

    Exciting laptop concept turns palm rest into an E ink notepad

    February 28, 2026

    AYN Thor and Odin 3 new pricing revealed, to take effect in March

    February 28, 2026
    Leave A Reply Cancel Reply

    Top Posts

    Ping, You’ve Got Whale: AI detection system alerts ships of whales in their path

    April 22, 2025699 Views

    Lumo vs. Duck AI: Which AI is Better for Your Privacy?

    July 31, 2025280 Views

    6.7 Cummins Lifter Failure: What Years Are Affected (And Possible Fixes)

    April 14, 2025162 Views

    6 Best MagSafe Phone Grips (2025), Tested and Reviewed

    April 6, 2025124 Views
    Don't Miss
    Gadgets March 1, 2026

    Infinix launches NOTE 60 Series in Malaysia

    Infinix launches NOTE 60 Series in Malaysia Infinix has unveiled the new Infinix NOTE 60…

    Razer’s laptop sleeve comes with MagSafe wireless charging for US$130

    Apple’s Rumoured Budget MacBook Could Arrive With Notable Feature Trade-Offs

    The compact smartphone I actually want: Xiaomi 17 in a Galaxy S26 world

    Stay In Touch
    • Facebook
    • Twitter
    • Pinterest
    • Instagram
    • YouTube
    • Vimeo

    Subscribe to Updates

    Get the latest creative news from SmartMag about art & design.

    About Us
    About Us

    Welcome to Tech AI Verse, your go-to destination for everything technology! We bring you the latest news, trends, and insights from the ever-evolving world of tech. Our coverage spans across global technology industry updates, artificial intelligence advancements, machine learning ethics, and automation innovations. Stay connected with us as we explore the limitless possibilities of technology!

    Facebook X (Twitter) Pinterest YouTube WhatsApp
    Our Picks

    Infinix launches NOTE 60 Series in Malaysia

    March 1, 20262 Views

    Razer’s laptop sleeve comes with MagSafe wireless charging for US$130

    March 1, 20262 Views

    Apple’s Rumoured Budget MacBook Could Arrive With Notable Feature Trade-Offs

    March 1, 20262 Views
    Most Popular

    7 Best Kids Bikes (2025): Mountain, Balance, Pedal, Coaster

    March 13, 20250 Views

    VTOMAN FlashSpeed 1500: Plenty Of Power For All Your Gear

    March 13, 20250 Views

    Best TV Antenna of 2025

    March 13, 20250 Views
    © 2026 TechAiVerse. Designed by Divya Tech.
    • Home
    • About Us
    • Contact Us
    • Privacy Policy
    • Terms & Conditions

    Type above and press Enter to search. Press Esc to cancel.